A new transportation connection in southwest London is now open to traffic, adding road capacity and improving access between growing residential and commercial areas.
The City of London has opened the Bradley Avenue extension between White Oak Road and Wharncliffe Road South, connecting two previously separate sections of the corridor. The completed connection establishes a continuous route between Wonderland Road South and the White Oaks area.
The municipality expects Bradley Avenue to accommodate approximately 25,000 vehicles daily as development continues in southwest London.
The project also involved widening the existing Bradley Avenue section between White Oak Road and Jalna Boulevard from two lanes to four lanes, providing consistent road capacity along the corridor.
Beyond the roadway extension, the construction programme incorporated several transportation and municipal infrastructure improvements.
New sidewalks and cycling paths were installed along the newly constructed section. Additional cycling infrastructure was also introduced alongside existing sidewalks between White Oak Road and Jalna Boulevard.
A new traffic signal at Bradley Avenue and Wharncliffe Road South was installed to improve intersection operations and provide turning access for motorists.
Underground infrastructure upgrades formed another component of the project. Water and sewer systems were improved to support existing infrastructure requirements and future development in the surrounding area.
Stormwater management work included:
These measures are intended to improve water quality and reduce flooding risks during periods of heavy rainfall.
Construction began in June 2025, with major road construction completed in time for the November 2026 opening.
The roadway became operational before winter, although additional work remains. Construction crews are expected to return in spring 2027 to complete final asphalt paving, landscaping and outstanding finishing activities.
The opening marks the completion of the project's major road construction phase, while the remaining seasonal work will address final surface and site improvements.
The Bradley Avenue project demonstrates how municipal road construction can combine transportation capacity improvements with cycling infrastructure, underground utilities and stormwater management.
For municipal infrastructure owners, civil contractors and utility providers, the development highlights the coordination required to deliver multiple infrastructure components within a single road corridor.
With an anticipated capacity of approximately 25,000 vehicles per day, the upgraded corridor is designed to serve transportation needs in southwest London while supporting existing and future development in the surrounding area.
Source: CTV News