Construction owners are facing increasingly different market conditions across building sectors as they prepare capital investment plans for 2027. Funding availability alone is not determining which developments advance, with procurement constraints, specialized labor shortages and infrastructure capacity also influencing project delivery decisions.
DPR Construction's fourth-quarter 2026 Market Conditions Report identifies a more selective investment environment, with owners placing greater emphasis on project feasibility, funding confirmation and realistic construction schedules.
National forecasts also point to uneven growth across the nonresidential market. The American Institute of Architects projects 3% growth in nonresidential building spending in 2027, while data center spending is forecast to increase 25%. Broader commercial construction spending is projected to grow by 1%.
Planning activity reflects similar differences. The Dodge Momentum Index recorded a 9.4% increase in institutional planning in September, while commercial planning declined 1.3%.
Procurement conditions remain a significant consideration for owners and contractors preparing upcoming projects.
DPR's supply chain analysis identifies extended lead times for several critical electrical and power-related components:
Equipment or material
Reported lead time
Generators
Approximately 56 weeks
Switchgear
Approximately 37 weeks
Automatic transfer switches
Up to 18 months
Some structural steel products
Quoted into Q4 2027
Material pricing also faces uncertainty. A proposed copper tariff of 15% beginning Jan. 1, 2027, increasing to 30% in 2028, could affect future procurement costs.
These conditions make early equipment identification, procurement planning and coordination with suppliers important considerations during preconstruction.
DPR's assessment identifies distinct investment priorities across its five core markets.
For construction owners, developers and general contractors, the changing investment environment places greater importance on project readiness before major financial commitments.
Confirmed funding, defined scopes, regulatory approvals, realistic schedules and early procurement planning can influence whether projects progress into construction.
The differences between sector forecasts also demonstrate why national spending projections alone may not provide a complete picture of market opportunities. Local labor availability, utility infrastructure and equipment supply conditions remain important factors in evaluating construction investments heading into 2027.
Source: DPR.