Highlights

  • Steel girder installation is underway for a new railway bridge at Calgary’s 6th Street S.E. Underpass.
  • The bridge will carry Canadian Pacific Kansas City (CPKC) trains over the future roadway.
  • The design-build project will connect Calgary’s Culture + Entertainment District with East Village.
  • The completed underpass will include four traffic lanes, pedestrian sidewalks and a multi-use pathway.
  • Construction includes utility relocations, stormwater infrastructure, road realignment and deep excavation.

Railway Bridge Construction Advances

Railway infrastructure and urban road improvements are progressing together in downtown Calgary, where a new underpass is being developed to improve connections between two major urban districts. EllisDon is advancing the 6th Street S.E. Underpass through steel girder installation for a new railway bridge that will carry CPKC trains above the future roadway.

The design-build project will create a connection between Calgary’s Culture + Entertainment District and East Village. The underpass is planned to accommodate four traffic lanes, wider pedestrian sidewalks and a multi-use pathway for cyclists and other active transportation users.

The infrastructure is also being designed to accommodate the future Green Line LRT and high-speed rail, while supporting development within the Culture + Entertainment District.

Construction Requires Continued Railway Operations

Maintaining active railway service has been a central consideration during bridge construction. A temporary railway alignment, known as a shoofly track, was constructed to allow trains to operate away from the original tracks while work progresses on the permanent bridge.

Once the new bridge is complete and operational, railway traffic will transition from the temporary alignment to the permanent route. This will open additional construction space beneath the railway for the roadway, pedestrian and cycling infrastructure, utilities and finishing work.

Other activities are progressing across the constrained urban site. Construction crews are lowering and realigning a section of 9 Avenue to connect with the underpass. Work also includes utility relocations, new stormwater infrastructure, groundwater management, drainage and deep excavation.

Coordinating these activities alongside railway operations and bridge construction requires multiple work areas to progress within the same urban corridor.

Underpass Design and Transportation Features

The completed structure will introduce Calgary's first clear-span bridge of this type, without centre support columns. The design will provide more open sightlines beneath the railway structure.

Additional features include architectural lighting, brick finishes and landscaping intended to integrate the infrastructure with the surrounding urban environment.

The wider pedestrian routes and multi-use pathway will provide dedicated space for active transportation alongside the four-lane roadway. The design also accounts for future transit and rail infrastructure requirements.

Infrastructure Connections for Calgary's Urban Development

The 6th Street S.E. Underpass represents a transportation infrastructure investment supporting connectivity between Calgary's Culture + Entertainment District and East Village.

For construction contractors and infrastructure stakeholders, the project involves coordinating railway operations, bridge installation, roadway modifications, underground utilities and drainage within a restricted urban footprint.

Its delivery also demonstrates the construction considerations involved in developing new road connections beneath operational railway infrastructure while accommodating future transportation requirements.

Source: EllisDon 75.

Get the inside scoop on the latest trending construction industry news and insights delivered straight to your inbox.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.