F.H. Paschen Completes $32 Million Union Ridge School Expansion and Renovation on Schedule

Construction Owners Editorial Team

Harwood Heights, IL – November 18, 2026 – F.H. Paschen has completed a $32 million expansion and renovation project at Union Ridge School District 86 in Harwood Heights, Illinois, delivering new classrooms and facility upgrades ahead of the 2026-27 school year. The project was completed within the district's approved referendum budget and included $8 million in additional improvements to the existing school building.

The project follows a wave of school construction referendums approved by Illinois voters, representing more than $1.3 billion in funding for K-12 facility improvements. Districts across the state are planning classroom additions, security improvements and renovations to aging school buildings.

Highlights

  • F.H. Paschen completed a $32 million expansion and renovation at Union Ridge School District 86.
  • The project delivered a 38,000-square-foot addition with 12 new classrooms.
  • An additional $8 million in renovations upgraded the existing 1970s-era school building.
  • Nearly 20 bid alternates were developed to provide flexibility in managing the construction budget.
  • More than 30 in-house estimators tracked Chicago-area subcontractor pricing and equipment lead times.
  • The project was completed in time for the fall 2026 school opening.
  • Illinois voters approved more than $1.3 billion in K-12 school construction bond referendums.

School Expansion Addresses Modern Learning and Security Needs

Union Ridge School serves approximately 660 students from pre-kindergarten through eighth grade. Before the renovation, the original 1970s-era facility faced space constraints, limited accessibility and outdated security arrangements.

The expansion added 38,000 square feet of space, including 12 classrooms, a library, cafeteria, administrative offices, two flexible learning laboratories, academic support spaces and an ADA-accessible elevator.

The project also included a redesigned main entrance with a single-point security vestibule based on Crime Prevention Through Environmental Design (CPTED) principles. A modern fire alarm system was installed across the campus.

F.H. Paschen was appointed as construction manager before the design of the new addition was completed, allowing the company to contribute to early planning, cost evaluation and budget management.

Mike Maguire, superintendent of Union Ridge School District 86, said the project delivered the classrooms, laboratories and cafeteria required by students while also enabling additional improvements to the existing facility.

Preconstruction Planning Unlocks $8 Million in Additional Upgrades

F.H. Paschen collaborated with Union Ridge School District 86 and project architect ARCON Associates during design development to align project requirements with current construction market conditions.

The company's team of more than 30 in-house estimators monitored regional subcontractor pricing, labor costs and equipment availability. Building Information Modeling (BIM) and digital site tools were also used to identify potential structural conflicts before construction activities began.

To maintain budget flexibility, the team developed nearly 20 bid alternates before issuing bid packages. This allowed the district to consider additional improvements if competitive subcontractor bids created savings.

Favorable trade bids enabled the district to accept six alternates initially. As foundation and underground utility work progressed without requiring contingency funds, additional savings were redirected toward improvements to the existing school.

Working with ARCON Associates, F.H. Paschen completed $8 million in upgrades to the original building over an eight-week summer construction period. Improvements included replacing windows, ceilings, lighting and flooring, along with upgrading the fire alarm system.

Josh Curran, vice president and director of K-12 construction at F.H. Paschen, said early planning and multiple preconstruction scenarios helped the district maximize its available funding while protecting the project's scope and schedule.

Construction Management Strategies for Illinois School Districts

The Union Ridge project offers lessons for school districts preparing to deliver construction programs following recently approved referendums.

F.H. Paschen identified seven considerations for selecting a K-12 construction manager:

  1. Subcontractor competition: Established trade relationships can generate multiple competitive bids and help control costs.
  1. Current market pricing: Dedicated estimators should monitor regional labor rates, material prices and long-lead equipment schedules.
  1. Pre-priced alternatives: Bid alternates provide opportunities to expand project scope when savings become available.
  1. Construction technology: BIM coordination, digital site tracking and scheduling tools can identify potential problems before field construction.
  1. Occupied-campus experience: Construction managers must maintain safe school operations while completing additions and renovations.
  1. Transparent communication: Collaboration among construction managers, architects, school boards and communities supports budget and schedule accountability.
  1. On-time school openings: Experience meeting August school opening deadlines is essential for education construction projects.

Why It Matters

Illinois school districts have secured more than $1.3 billion in approved construction bond funding, increasing the need for effective project planning and cost management. The Union Ridge project demonstrates how early construction manager involvement, competitive subcontractor procurement and preconstruction planning can help schools maximize taxpayer-funded investments while delivering modern learning environments on schedule.

Source: F.H. Paschen.