FlatironDragados Completes First Water Release Test at Anderson Dam Tunnel

Construction Owners Editorial Team

Highlights

  • FlatironDragados has completed a controlled water-release test at the Anderson Dam Tunnel in Morgan Hill, California.
  • Approximately 4 million gallons of water passed through the new outlet system during testing.
  • Crews tested two 11-foot-diameter fixed cone valves individually at 10% capacity.
  • The tunnel will improve water-release capacity from Anderson Reservoir into Coyote Creek.
  • The successful test advances preparations for the Anderson Dam Seismic Retrofit project.

Upgraded water-release infrastructure is a critical prerequisite for major dam rehabilitation projects, particularly where reservoir operations must be managed during reconstruction. A controlled test at California's Anderson Dam has demonstrated the operation of a new diversion outlet system designed to improve reservoir-level management and support a broader seismic safety upgrade.

Anderson Dam Tunnel Demonstrates Outlet System Performance

FlatironDragados completed a controlled water-release test at the Anderson Dam Tunnel in Morgan Hill, California, with approximately 4 million gallons of reservoir water discharged into Coyote Creek.

The November 24, 2026, milestone involved testing two fixed cone valves, each measuring 11 feet in diameter. Construction crews gradually opened the valves to approximately 10% capacity, testing them individually to monitor downstream water flow before activating the second valve.

The test demonstrated the operation of the new outlet infrastructure, which was developed for Valley Water, the project's client.

Diversion Tunnel Supports Dam Reconstruction

The new tunnel and diversion outlet system are designed to increase the volume of water that can be released from Anderson Reservoir into Coyote Creek.

The improved discharge capacity will allow Valley Water to manage reservoir levels during periods of heavy rainfall and throughout reconstruction of the existing dam.

The tunnel project is a prerequisite for the Anderson Dam Seismic Retrofit, which is intended to bring the dam into compliance with current seismic safety standards.

FlatironDragados is delivering the tunnel and is also working with Sukut on the dam and spillway reconstruction and outlet system reconfiguration.

Seismic Retrofit Advances Regional Water Infrastructure

The broader retrofit program aims to improve Anderson Dam's seismic resilience and enable Santa Clara County's largest reservoir to return to full operating capacity.

For water infrastructure owners and contractors, the project demonstrates how advance diversion systems can support complex rehabilitation work while maintaining controlled reservoir operations.

The successful valve test establishes an operational milestone for the new release system and supports the next phase of work associated with the dam's reconstruction and seismic upgrades.

Source: FD Corp.