Modernizing aging flood-control infrastructure can improve reservoir management and strengthen protection for communities downstream. At Folsom Dam in California, a major spillway gate has completed its first full operational movement following extensive structural and mechanical rehabilitation.
Folsom Dam Constructors, a joint venture between CEC and Shimmick, achieved the milestone on Gate 8 as part of the Folsom Dam Raise Project for the U.S. Army Corps of Engineers.
The successful operation marks the beginning of the gate's commissioning process and establishes a reference point for retrofitting the remaining seven gates.
Gate 8 measures approximately 42 feet wide and weighs 150 tons. Retrofit work began in March 2025 and involved temporarily taking the gate out of service and supporting the structure while crews completed modifications.
The rehabilitation scope includes:
During its first full opening, the reconstructed gate rotated upward through its complete operating range, achieving 42 vertical feet of lift.
The successful movement demonstrates that the upgraded structural and mechanical components can operate through the gate's full travel range. Gate 8 is now entering commissioning before returning to service.
The retrofit involves working within an existing dam structure while meeting technical and operational requirements for critical flood-control infrastructure.
Folsom Dam Constructors has coordinated engineering activities with the U.S. Army Corps of Engineers through a weekly technical task force. The meetings bring together engineering representatives from both organizations to evaluate construction challenges, develop technical solutions and coordinate implementation.
Gate 8 serves as the project's initial demonstration of the retrofit design and construction approach. Lessons from the first gate will inform the work planned for the remaining seven spillway gates.
The wider Folsom Dam Raise Project involves upgrading all eight existing spillway gates to improve flood management capabilities.
Once the improvements are implemented, Folsom Lake will be able to temporarily accommodate an additional 3.5 feet of water during major storm events. The increased storage capacity is intended to provide greater flexibility in reservoir management and controlled downstream water releases.
The additional capacity is expected to help reduce flood risks for Sacramento and surrounding communities.
For public infrastructure owners and water-sector contractors, the project demonstrates the engineering and construction coordination required to rehabilitate major operating infrastructure without replacing the entire facility. The staged gate retrofit approach also allows the project team to apply technical lessons from the initial installation to subsequent work.