News
November 10, 2026

Sturgeon Electric Earns NECA Award for Alaska Highway Lighting and Signal Project

Construction Owners Editorial Team

A 4.5-mile highway improvement project along Alaska’s Glenn Highway has earned Sturgeon Electric Company a 2026 Project Excellence Award from the National Electrical Contractors Association (NECA), recognising the electrical contractor’s work on streetlighting and traffic signal upgrades.

Sturgeon Electric, a subsidiary of MYR Group, completed the electrical scope for the project covering the Parks Highway to South Inner Springer Loop. The improvements were designed to increase visibility, improve traffic flow and support safer travel along a heavily used transportation corridor near Anchorage.

Highlights

  • Sturgeon Electric received a 2026 NECA Project Excellence Award.
  • The work supported a 4.5-mile highway reconstruction project in Alaska.
  • Electrical installations included approximately 60,000 feet of conduit and 127 lighting fixtures.
  • The team installed two traffic signal systems, 36 pile foundations and 91 cast-in-place concrete foundations.
  • Construction required underground utility verification, railroad coordination and accelerated scheduling during Alaska’s short construction season.

Electrical Scope Expanded With Highway Reconstruction

The project initially involved lighting and signal improvements at two intersections but expanded into a broader highway reconstruction effort. The two-lane roadway was widened to four lanes, intersection layouts were revised and additional intersections were incorporated.

Working under the general contractor, Sturgeon Electric delivered the complete electrical scope. Work included approximately 60,000 feet of conduit, most of it installed underground, 127 lighting fixtures and two traffic signal systems. The signal installations included traffic control cabinets and poles with mast arms ranging from 50 to 70 feet.

The expanded project required adjustments to construction sequencing as roadway configurations and intersection designs changed during execution.

Utility Verification and Railroad Coordination Supported Safe Construction

Existing underground utility records did not accurately reflect field conditions, creating potential conflicts between planned pile foundations and nearby water and sewer infrastructure.

Sturgeon Electric paused pile foundation installation and introduced a verification process using potholing to confirm utility locations and depths. Coordination with the general contractor and foundation subcontractor helped establish safe work sequences.

The team completed all 36 pile foundations and 91 cast-in-place concrete foundations without damaging underground utilities or causing significant project delays.

Sturgeon Electric also self-performed trenching and backfill operations, involving approximately 42,000 feet of excavation. Boring beneath active railroad crossings required additional coordination with railroad operations, and the work was completed without disrupting rail traffic.

Preconstruction Planning Addressed Alaska's Short Building Season

Alaska's limited construction season required early procurement, prefabrication and extended field schedules. Sturgeon Electric assembled mast heads and signal poles in a controlled environment during winter to prepare equipment for installation when weather conditions permitted.

During the peak construction period, crews worked six-day weeks with 10-hour shifts for approximately three months. These measures helped the team maintain productivity within the available construction window.

Why the Award Matters to Transportation Contractors

The project demonstrates the coordination required to deliver electrical infrastructure within complex highway reconstruction work. Underground utility verification, railroad crossing operations and changing roadway designs created challenges that required adjustments to field execution.

For transportation owners and contractors, the project also highlights how early procurement, prefabrication and detailed construction planning can support delivery in regions with short seasonal work windows. The completed lighting and signal improvements are intended to support safer, more efficient travel along the Glenn Highway corridor.

Source: MYR Group.

Get the inside scoop on the latest trending construction industry news and insights delivered straight to your inbox.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.