Clearway Construction Secures $13.5 Million University Avenue Infrastructure Contract in Toronto

Construction Owners Editorial Team

Highlights

  • The City of Toronto awarded Clearway Construction Inc. an approximately $13.5-million contract for infrastructure and road improvements along University Avenue.
  • Work includes watermain and water-service replacements, bikeway construction and major road resurfacing.
  • The overall project extends from College Street to approximately 120 metres north of Queen Street West.
  • Construction began in August 2026 under a revised schedule, with completion anticipated in spring 2027.
  • The project was deferred to coordinate with Metrolinx construction and preparations for the 2026 FIFA World Cup.

University Avenue Contract Covers Water and Road Infrastructure

Water infrastructure renewal and cycling improvements are among the key components of a $13.5-million project underway along University Avenue in Toronto. The City of Toronto awarded Clearway Construction Inc. contract 24ECS-LU-06SU to complete watermain and water-service replacements, bikeway construction and major road resurfacing.

The overall project area runs from College Street to approximately 120 metres north of Queen Street West. The watermain construction portion identified by the City extends from Armoury Street to College Street.

Revised Schedule Aligns With Major City Activities

The project was deferred to coordinate with ongoing Metrolinx construction and preparations for the 2026 FIFA World Cup. Under the revised schedule, construction started in August 2026, with completion expected in spring 2027.

The adjusted timing places the infrastructure work within a period of significant activity in Toronto, requiring coordination with other construction and event-related preparations.

Infrastructure Renewal and Construction Coordination

The contract combines underground utility replacements with surface transportation improvements along a major Toronto corridor. Watermain and water-service work will address municipal water infrastructure, while the bikeway and resurfacing components will deliver changes to the street's cycling and road facilities.

For Toronto's construction sector, the project highlights the coordination required when municipal infrastructure upgrades overlap with transit construction and preparations for major public events. Clearway Construction's work is scheduled to continue into spring 2027.

Source: Local 793.