News
June 27, 2026

PC Construction Advances Solids Upgrade Program at AlexRenew Wastewater Facility

Construction Owners Editorial Team

Highlights

  • PC Construction is progressing on a major solids handling upgrade at the AlexRenew Water Resource Recovery Facility in Alexandria, Virginia.
  • The project is part of AlexRenew’s long-term infrastructure modernization plan for wastewater treatment operations.
  • Work includes digester rehabilitation, centrifuge installation, piping replacement and electrical system upgrades.
  • Construction crews completed complex gas valve replacement and piping work while maintaining ongoing plant operations.
  • Full project completion is scheduled for 2029.

Wastewater utilities across the United States continue investing in long-term treatment plant modernization programs to improve operational reliability, process efficiency and regulatory compliance. PC Construction is advancing a major infrastructure upgrade at the AlexRenew Water Resource Recovery Facility in Alexandria, Virginia, as part of the utility’s multi-decade capital improvement strategy.

Courtesy: Photo by PC Construction

The Solids Upgrade Program involves extensive improvements to solids handling systems at a facility that serves more than 300,000 residents and processes approximately 38 million gallons of wastewater per day.

Solids Handling and Process Improvements

Project work spans multiple areas of the wastewater treatment facility’s solids management operations.

Scope elements include replacement of sludge heat exchangers, rehabilitation of digesters and gravity thickeners, installation of new centrifuge systems and upgrades to sludge blending and equalization equipment.

Additional construction activities include demolition of existing pre-pasteurization and lime systems, installation of a new polymer system and electrical upgrades required to support new process equipment.

PC Construction said early-stage activities included demolition work, pilot mixer installation and placement of new sludge heat exchangers during preconstruction operations.

Complex Utility and Piping Work

The contractor also completed several technically complex infrastructure tasks while maintaining active facility operations.

One major operation involved replacement of gas valves in an occupied facility where portions of the gas system could not be shut down. Construction crews implemented continuous flammability monitoring, ventilation controls and nitrogen-assisted gas isolation procedures to complete valve replacement work without interrupting plant operations.

Additional work included demolition and replacement of deteriorated piping systems tied to hot water supply infrastructure. Temporary piping systems were installed to maintain service continuity before crews completed permanent pipe installation and associated welded and mechanical connections.

PC Construction also completed a gas line purge and valve installation operation that had previously delayed progress on the project.

Wastewater Infrastructure Investment Continues

For construction owners and contractors, the AlexRenew project reflects ongoing investment in water and wastewater infrastructure modernization across U.S. utility systems.

Treatment plant upgrades increasingly require phased construction planning, complex process coordination and execution within active operating environments. Contractors specializing in water infrastructure continue facing demand for mechanical, process piping and utility system expertise as municipalities advance long-term capital improvement programs and regulatory compliance initiatives.

Source: PC Construction

Get the inside scoop on the latest trending construction industry news and insights directly in your inbox.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.