Downtown infrastructure improvements in Brantford, Ontario, are progressing with temporary road restrictions and overnight construction planned through the week of Nov. 23. The work includes infrastructure installation at the Brant Avenue and Dalhousie Street intersection, followed by planned traffic configuration changes in early December.
The City has scheduled overnight construction for Wednesday, Nov. 25, from 8 p.m. to 6 a.m., weather permitting. During the work, Brant Avenue will be reduced to a single southbound lane, with detours in place.
Colborne Street will temporarily reopen to a single eastbound lane during the overnight operation. Two-way traffic on Brant Avenue is expected to resume between 6 a.m. and 8 p.m.
Existing restrictions include lane reductions on Dalhousie Street and Brant Avenue, a single eastbound lane on the Lorne Bridge, and closures on Colborne Street and Bridge Street. Westbound traffic on the Lorne Bridge remains open.
The reopening of Colborne Street and closure of Dalhousie Street are tentatively scheduled for early December, subject to weather conditions. A single-lane restriction on Colborne Street may remain while watermain work is completed.
The City expects the construction work to finish in late December 2026. Motorists, cyclists and pedestrians are advised to follow posted signs and allow additional travel time.
Veterans Memorial Parkway remains open without construction-related obstructions. The City is also encouraging drivers to use both lanes approaching merge points and take turns to help reduce congestion.
The downtown project involves infrastructure work across several streets, requiring temporary traffic changes and coordination with local businesses. Maintaining access for residents, visitors and commercial properties remains an important consideration as the City completes the work. The project is funded in part by the governments of Canada and Ontario.
Source: Brantford.