Ames Construction Completes Interim Repairs on Santa Fe Drive to C-470 Flyover Bridge

Construction Owners Editorial Team

Highlights

  • Ames Construction and the Colorado Department of Transportation completed interim repairs on the Santa Fe Drive to eastbound C-470 flyover bridge.
  • The project restored structural support by replacing the pier cap and column at Pier 7.
  • Construction began in February and concluded in late July while maintaining traffic through phased operations.
  • A temporary seven-day ramp closure enabled critical concrete work and curing before reopening the bridge.

Maintaining aging bridge infrastructure remains a priority for transportation agencies seeking to improve roadway safety and network reliability. Ames Construction, working with the Colorado Department of Transportation (CDOT), has completed interim structural repairs on the flyover bridge connecting southbound Santa Fe Drive (US 85) to eastbound C-470 in Douglas County, Colorado.

The work restored structural integrity at a key bridge support while allowing the interchange to remain operational for most of the construction period.

Structural Repairs Restore Bridge Support

Construction crews replaced the pier cap and supporting column at Pier 7, restoring structural capacity at the affected section of the bridge. Additional work included installing temporary shoring and structural monitoring equipment, completing concrete repairs and reconnecting the repaired components to the existing bridge structure.

The repair program began in February and was delivered in phases to minimize traffic disruptions. A planned seven-day closure of the flyover ramp allowed crews to complete concrete placement and provide sufficient curing time before the bridge reopened to motorists.

Phased Construction Minimized Traffic Impacts

Project sequencing enabled traffic to continue using the interchange throughout most of construction while targeted closures supported critical structural work.

Completion of the interim repairs improves the safety and operational reliability of the flyover connection serving traffic traveling from southbound US 85 to eastbound C-470.

Why It Matters

Bridge rehabilitation projects remain an essential component of transportation asset management programs as agencies work to extend the service life of existing infrastructure. For construction owners and contractors, phased repair strategies help maintain traffic flow while addressing structural deficiencies, reducing disruption for motorists and supporting long-term infrastructure performance.

Source: Ames Construction.