Construction is progressing across multiple education facilities at the WSWHE BOCES campus in Wilton, New York, with work advancing through enclosure, roofing, framing, interior finishes and mechanical preparation.
BBL Construction Services is managing construction activities across the campus, which includes a Career and Technical Education Center and facilities serving exceptional learners at different grade levels.
The Career and Technical Education Center is nearing enclosure as exterior construction advances. Exterior finishes have begun, while crews are also painting interior laboratory spaces.
The progress marks a transition toward completing the building envelope and advancing interior work within the career-focused education facility.
Construction is progressing at two additional facilities serving exceptional learners.
At the K-6 Exceptional Learners Center, roofing work remains underway as the project team prepares for upcoming slab pours.
The 7-12 Exceptional Learners Center has progressed further. Roofing and slab pours have been completed, with structural framing now underway. Drywall installation is progressing on the third floor, and mechanical rough-in work is scheduled to follow.
The different construction stages across the three facilities reflect a phased campus development program, with crews simultaneously completing exterior, structural and interior activities.
The WSWHE BOCES campus project demonstrates the coordination required to deliver multiple education facilities with different construction schedules and scopes within one campus.
For school owners and construction managers, sequencing work across buildings allows structural, envelope, interior and mechanical activities to advance concurrently while maintaining progress across the broader campus program.
Source: BBL.