News
November 1, 2026

Clark Completes 56-Day Metro Upgrade at Two WMATA Red Line Stations

Construction Owners Editorial Team

Highlights

  • Clark Civil completed major structural and platform upgrades during a 56-day shutdown at two Washington-area Metro stations.
  • Work covered Bethesda and Grosvenor-Strathmore stations on the Washington Metropolitan Area Transit Authority's (WMATA) Red Line.
  • The improvements included a new mezzanine at Bethesda and platform rehabilitation at Grosvenor-Strathmore.
  • Crews removed more than 18,000 square feet of platform tile and concrete topping slab at Grosvenor-Strathmore.
  • Bethesda station work is progressing toward a planned 2027 completion.

Two Metro Stations Receive Major Structural Improvements

Coordinating complex rail infrastructure upgrades within a limited service shutdown requires close sequencing of demolition, structural construction and platform work. Clark Civil completed a concentrated 56-day construction programme at two WMATA Red Line stations in the Washington, D.C., region to advance transit modernization while limiting disruption to passengers.

The work took place at Bethesda and Grosvenor-Strathmore stations, which collectively serve approximately 18,000 passengers daily. Crews operated around the clock during the summer shutdown to complete major improvements at both locations.

Bethesda Mezzanine and Grosvenor-Strathmore Platform Work

At Bethesda station, construction includes a new mezzanine connecting the Red Line with the Maryland Transit Administration's Purple Line light rail system.

Following a 44-hour demolition operation in November, crews installed structural steel, applied fireproofing and placed structural concrete. The team also used compact spider cranes to handle steel and precast components within the station's restricted access areas.

At Grosvenor-Strathmore station, the work represented the first major platform overhaul since the facility opened in 1984.

Construction activities included:

  • Removing more than 18,000 square feet of platform tile and concrete topping slab.
  • Replacing approximately 1,200 linear feet of track-edge components.
  • Completing work along the station's 600-foot platform.
  • Using remote-controlled demolition equipment to remove existing materials.

The platform work was completed in less than two weeks.

Construction Logistics and Structural Challenges

Working within active transit infrastructure presented significant access and engineering challenges. Historical station drawings from the 1970s and 1980s did not always reflect actual field conditions, requiring coordination among Clark Civil, WMATA, architects and structural engineers to resolve discrepancies during construction.

Equipment deliveries also required specialised planning because rail power was disconnected during the shutdown. Machinery and materials were transported using diesel locomotives and flatbed rail cars.

Concrete placement required different approaches at the two stations.

At Grosvenor-Strathmore, crews scheduled concrete pours for 4 a.m. to manage high summer temperatures and maintain concrete quality. More than 280 cubic yards of concrete were placed during cooler morning conditions.

At Bethesda, the absence of a direct vertical pumping route required a 500-foot concrete delivery pipeline routed through existing access tunnels. A specially developed concrete mix supported placement through the extended pipeline. The team also installed 60% of the mezzanine's precast panels ahead of schedule for subsequent construction activities.

The 56-day shutdown was completed without reported safety incidents.

Implications for Transit Infrastructure Contractors

The project highlights the construction planning required to modernize aging rail facilities while working within restricted shutdown windows. Demolition sequencing, specialised equipment, concrete logistics and rapid field coordination were central to completing the scheduled work.

For transit agencies and contractors, the upgrades demonstrate how concentrated construction periods can advance major structural improvements while reducing the duration of service interruptions.

Grosvenor-Strathmore's modernization work is complete, while Bethesda station construction continues toward its anticipated 2027 completion.

Source: Clark Construction.

Get the inside scoop on the latest trending construction industry news and insights directly in your inbox.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.