Airport construction projects face tight schedules, active-airfield constraints and complex coordination requirements. Hensel Phelps is addressing these challenges through project-specific construction methods across three major airport programmes in Seattle, Columbus and San Antonio, focusing on resolving risks before work reaches the field.
The company's approaches include custom-designed scanning equipment, off-site building enclosure fabrication and early coordination between structural steel and mass timber trade partners.
At Seattle-Tacoma International Airport, Hensel Phelps is completing the $437 million Port of Seattle Baggage Optimization Phase 3 project, the final stage of consolidating six independent baggage screening systems into one.
Work in the congested baggage handling area required reliable survey control points for laser scanning, clash detection and as-built verification. Commercial scanning targets were expensive and difficult to install in the confined space, with installation also posing a risk of damaging fireproofing on structural steel.
The project’s virtual design and construction team developed reusable 3D-printed targets consisting of a frame, removable spike and target plate. The design allows the targets to be installed through the fireproofing without scraping it away.
Each target costs approximately $1.25 to produce. The team placed hundreds throughout the baggage area, reducing scan registration time from as much as a full day to minutes. The digital design files can also be shared with other project teams that have access to 3D printers.
At John Glenn Columbus International Airport, Hensel Phelps and Columbus-based Elford are delivering the $1.6 billion New Midfield Terminal under a construction manager at risk arrangement. The 1-million-square-foot terminal is designed to accommodate more than 13 million passengers annually and is scheduled for completion in 2029.
To address labour constraints, weather exposure and schedule pressures associated with traditional building enclosure work, the project team shifted much of the fabrication off site.
Level one uses architectural precast panels manufactured at a plant, while level two uses unitized wall assemblies with glass, framing and metal panels assembled and inspected before delivery. Early design-assist sessions, performance mock-ups and fabrication releases helped validate the systems before production.
The approach reduced installation time by 70% and field labour requirements by more than 90% compared with traditional methods. Curtain wall and metal panel costs decreased by 21%, while using precast instead of structural masonry reduced costs by 26%.
At San Antonio International Airport's Terminal Development Program, Hensel Phelps is integrating approximately 157,500 square feet of mass timber with structural steel. The structure includes 538 cross-laminated timber panels and 339 glue-laminated timber beams.
Because different design teams were responsible for the steel and timber connections, the project required detailed coordination to ensure the systems would fit together. The team also needed to address moisture protection and the integration of building services with the exposed timber finishes.
Hensel Phelps brought structural steel and mass timber trade partners into the design process. Over approximately six months, the teams held weekly design-assist meetings and three extended workshops to resolve details before construction documents were issued.
The company also established a direct contract with LeJeune Steel Company, which managed the steel erector and mass timber supplier Timberlab. This arrangement brought three major scopes under one contractual relationship.
LeJeune was contracted in July 2025, and materials began arriving on site in December 2025. Over approximately 10 months, the team installed 7,200 tons of structural steel, 1,100 tons of steel decking, all 538 CLT panels and all 339 glulam beams. The structure reached its topping-out milestone on October 14, 2026.
The three projects demonstrate how early risk identification and changes to construction processes can improve delivery on complex airport programmes. Custom scanning tools, off-site fabrication and coordinated procurement can reduce field labour, limit rework and address design conflicts before they affect construction.
For airport owners, these approaches offer practical ways to improve schedule predictability while managing construction around active operations and demanding infrastructure requirements.