MDOT Pauses $335 Million Marshall Highway Modernization Project for Winter

Construction Owners Editorial Team

Highlights

  • Michigan DOT is suspending construction on the Marshall Modernization Project during the winter, with work scheduled to resume in spring 2027.
  • The three-year program represents a $335 million investment in I-94, I-69 and M-96 improvements.
  • 2026 work included rebuilding westbound I-94, bridge reconstruction, interchange ramp improvements and drainage infrastructure.
  • 2027 construction will include rebuilding eastbound I-94 and the M-311 bridge over I-94.
  • The project supports transportation infrastructure serving the Marshall Area Jobs, Opportunity and Recreation (MAJOR) Campus.

A $335 million highway modernization program in Marshall, Michigan, is entering its winter construction pause after completing its second year of work. The Michigan Department of Transportation (MDOT) announced that construction on the Marshall Modernization Project would stop during the week of Nov. 16, with the next phase expected to begin in March 2027.

2026 Work Advances Interstate and Interchange Improvements

The second year of the three-year program focused on improvements to I-94, M-96 and connecting infrastructure supporting the Marshall Area Jobs, Opportunity and Recreation (MAJOR) Campus.

Work completed during 2026 included:

  • Rebuilding westbound I-94 between the Kalamazoo River and M-96 Exit 104.
  • Reconstructing the M-96/I-94 Business Loop bridge over I-94.
  • Rebuilding eastbound and westbound I-94 ramps at Exit 104.
  • Realigning the M-311 ramp to westbound I-94.
  • Installing three box culverts.
  • Realigning Dickinson Creek.

These improvements form part of the broader effort to rebuild and repave major highway connections in the Marshall area.

2027 Phase Includes Bridge and Eastbound Interstate Reconstruction

Construction is expected to resume in March 2027, beginning with demolition of the M-311 bridge over I-94 to allow reconstruction.

The next phase will also include rebuilding eastbound I-94 and its Exit 104 ramps, completing the M-96 boulevard conversion and reconstructing the Pigeon Creek box culvert beneath M-96.

The planned work will continue improvements to the interstate corridor and its connecting roads.

Winter Traffic Configuration and Project Schedule

During the seasonal pause, one lane in each direction will remain open on M-96 (Michigan Avenue) and M-311 (11 Mile Road). I-94 will maintain two open lanes in each direction, and all ramps at Exit 104 will remain accessible.

Why It Matters

The project demonstrates the scale of coordinated highway, bridge, interchange and drainage work required to modernize regional transportation infrastructure. For contractors, the upcoming 2027 phase will involve multiple construction activities, including bridge replacement, interstate reconstruction and drainage improvements, as the state continues its investment in the Marshall-area transportation network.

Source: MDOT.