News
May 20, 2026

Shimmick Challenges USACE Contract Termination on Tennessee Lock Project

Construction Owners Editorial Team

Infrastructure contractor plans formal appeal after federal agency ends its role on the Chickamauga Lock replacement project in Tennessee.

Highlights

  • Shimmick Corporation plans to appeal a contract termination issued by the U.S. Army Corps of Engineers related to the Chickamauga Lock replacement project.
  • The contractor was responsible for construction of the 600-foot lock chamber portion of the project.
  • The company said the project involved more than 5 million labor hours and a peak workforce exceeding 425 workers.
  • Shimmick disputes the termination decision and intends to pursue compensation tied to project-related costs.
  • The contractor continues to perform work on other active USACE projects in Texas and California.

Shimmick Corporation announced plans to formally challenge a recent contract action by the U.S. Army Corps of Engineers involving the long-running Chickamauga Lock replacement project in Chattanooga, Tennessee.

Courtesy: Photo by Ali on Pexels

The dispute centers on a federal contract originally awarded in 2017 for construction of the project’s 600-foot lock chamber, including drilled shaft foundations, mass concrete work, and installation of miter gate systems and related infrastructure components.

According to the company, the USACE issued a notice terminating Shimmick’s right to proceed under the contract earlier this month. The contractor said it intends to exercise its contractual appeal rights within the allowable review period.

The Chickamauga Lock replacement has been one of the more complex inland waterway infrastructure projects currently underway in the United States, involving large-scale concrete operations, marine construction, and extensive coordination among federal agencies, subcontractors, and labor forces.

Shimmick stated that project teams accumulated more than 5 million labor hours over the course of the assignment while employing a peak workforce of more than 425 personnel on site, including local subcontractors and union labor partners.

The contractor also indicated that project challenges involved ongoing change-order discussions and evolving construction conditions, both of which are common on large-scale federal infrastructure projects with long durations and complex technical scopes.

Disputes tied to change orders, schedule impacts, and differing site conditions remain a recurring issue across major public infrastructure work, particularly on multiyear civil megaprojects where design revisions, unforeseen conditions, and scope modifications can significantly affect project execution and cost structures.

The appeal process could draw attention from contractors and public owners alike because of its potential implications for risk allocation, claims management, and contractor-government relations on future federally funded infrastructure projects.

Despite the dispute, Shimmick said it continues to maintain active working relationships with the USACE through ongoing infrastructure assignments in Texas and California.

The company specializes in large-scale water, transportation, energy, and climate resilience infrastructure projects throughout the United States.

What This Means for Construction Owners

For construction owners and public agencies, the dispute highlights the growing complexity and contractual risk associated with large-scale infrastructure megaprojects. Long-duration civil projects often involve evolving site conditions, design revisions, and extensive change-order negotiations that can significantly affect schedules, costs, and contractor relationships.

The case also underscores the importance of clearly defined contract administration processes, documentation standards, and dispute resolution mechanisms on federally funded work. Owners managing major infrastructure programs may increasingly focus on collaborative delivery methods, early risk identification, and transparent change management practices to reduce the likelihood of costly project disputes.

For contractors pursuing public-sector megaprojects, the situation serves as another reminder that claims management, labor coordination, and contractual flexibility remain critical components of successful project execution in today’s infrastructure market.

Originally reported by Shimmick.

Get the inside scoop on the latest trending construction industry news and insights directly in your inbox.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.